01Stage 1 · Care and assisted living
The building permit dated 19 November 2024 and construction clearance dated 30 June 2025 are in place. The plan comprises 98 care places, 13 assisted-living apartments and one staff apartment. According to the project records, architecture, electrical systems, building services, external works and fire protection have been developed through German service phase 5.
02Stage 2 · Independent housing
The second phase provides for around 41 to 42 assisted-living units. According to the project records, the approval design was submitted in October 2025; supplementary information and the final unit count will be clarified as the process continues.
03Stage 3 · Flexible residential neighbourhood
The legally binding development plan provides the basis for around 100 to 150 additional homes. Concept planning, site topography and preliminary planning for roads and utilities are available; product mix, construction phases and marketing strategy remain flexible.